Power and data centers
US data centers have announced more than 115 GW of their own gas plants, enough to add 152 Mt of CO2 a year
Speed to power is pulling AI campuses off the grid. Utilities are answering with long contracts and big upfront charges, while drought maps show where cooling water could run short.
More than 100 behind-the-meter gas plants had been announced at US data centers by October 2026, totaling over 115 GW, more than double California's peak demand, MIT Technology Review reported Nov 24, citing Cleanview. About 4.9 GW is operating and 15.8 GW is under construction. BloombergNEF counts 181 GW of on-site data center gas announced worldwide, 90% of it in the US, and estimates the planned US plants could emit 345 million tonnes of CO2e a year by 2035, 152 million tonnes more than drawing the same power from the grid.
Utilities are pricing that load in. TVA disclosed $1.7 billion in aggregate payments from one unnamed data center customer under its new large-load rate, which charges about $1.5 million per MW of requested capacity above 5 MW, Utility Dive reported Nov 24. In North Carolina, regulators now require qualifying data centers to sign contracts of at least 10 years, pay demand charges on at least 75% of contracted capacity and post guarantees against stranded costs, WRAL reported.
Water is the next constraint. A BMI note published Nov 24 found that about 21% of 83.6 GW of tracked global data center capacity sits where El Niño raises water stress, with 14.9 GW highly exposed, 92% of it in Asia Pacific. In Nevada, a Desert Research Institute study estimates proposed data centers could use about 12,770 acre feet a year for cooling by 2036, plus 21,283 acre feet indirectly through power generation.
Sources: MIT Technology Review, Nov 24, 2026; Utility Dive, Nov 24, 2026; WRAL, Nov 24, 2026; TNGlobal, Nov 24, 2026; Facilities Dive, Nov 20, 2026; Utility Dive, Nov 23, 2026; Carbon Herald, Nov 24, 2026